Guide · Updated 2026-10-23

Dubai Approvals in Numbers: Statistics and Timelines (2026)

Last updated: October 2026. Figures come from DEWA, RTA and UAE government sources, linked below each table. We update this page when new figures are published.

Key numbers at a glance

  • DEWA approved 132,981 NOC applications in 2025, up 4.49% on 2024.
  • Those 2025 applications came from 2,472 consultants and contractors.
  • In the first half of 2026, DEWA approved 61,183 NOC applications under its Soqoor programme.
  • DEWA's infrastructure NOC is free and is delivered in 3 to 7 working days, depending on type.
  • New commercial and industrial electricity connections of up to 150 kW can be completed in 5 days through DEWA's Al Namoos service.
  • Public EV charging at DEWA EV Green Chargers costs AED 0.70 per kWh (AC) and AED 1.20 per kWh (DC), plus VAT.
  • Home EV charging is billed at standard residential rates on your normal DEWA bill.

DEWA NOC approvals in 2025

DEWA approves No Objection Certificates for consultants and contractors through its Soqoor programme.

DEWA divisionNOC applications approved (2025)Share
Transmission Power69,81652.5%
Distribution Power45,41834.2%
Water and Civil17,74713.3%
Total132,981100%

Total applications rose 4.49% compared with 2024. Shares are calculated from DEWA's published figures.

Source: DEWA, "DEWA records 4.49% rise in NOC approvals amid growing project activity", 12 February 2026.

DEWA infrastructure NOC: review times

NOC typeDEWA delivery time
Informational services3 working days
Trial pits NOC3 working days
House connection NOC3 working days
Dubai Building Permit System (DBPS) NOC3 working days
General NOC5 working days
Network projects NOC7 working days
Road projects NOC7 working days

The service is free. Consultants, contractors, developers and registered service authorities can apply. Projects in the Right of Way go through RTA's eNOC system (noc.rta.ae). Projects within or next to DEWA premises go through the DEWA customer portal. DEWA notes that special cases can take longer.

Source: DEWA, Infrastructure Projects No Objection Certificate service page.

New electricity connections: Al Namoos

ItemDetail
Maximum loadUp to 150 kW
Time to connect5 days, in two steps
Who appliesElectrical contractors only
EligibleNew, permanent connections supplied from DEWA's existing network

After the connection fee is paid, DEWA completes the external work, installs the meter and connects the supply.

Source: DEWA, Al Namoos service page.

EV charging costs in Dubai

Where you chargeCost
DEWA EV Green Charger (AC)AED 0.70 per kWh + VAT
DEWA EV Green Charger (DC fast)AED 1.20 per kWh + VAT
At homeStandard DEWA residential rate, on your normal bill
EV Green Charger account security depositAED 500 (government entities exempt)

Public charging rates are set by Cabinet Decision No. 81 of 2024. Under Dubai Directive No. 1 of 2017, organisations and developers need DEWA approval before installing EV charging stations.

Source: DEWA, EV Charging and EV Green Charger FAQs.

Timelines from our own projects

ApprovalTypical time, start to certificateWhat usually causes delays
DEWA additional load / power upgrade2 to 4 weeksPanel modifications, site readiness

These figures come from our own projects as a DEWA approved contractor in Dubai. They are our typical ranges, not authority guarantees. Authorities set their own timelines, and incomplete documents are the most common cause of delay.

How to cite this page

You're welcome to use these figures. Please link to this page as the source:
UAE Approval Hub, "Dubai Approvals in Numbers", uaeapprovalhub.com/guides/dubai-approvals-statistics-timelines/